Contract Planning, Strategy and Claims Management Training Course

Duration 10 days 20 modules · 65 contact hours
Level Intermediate Certificate on completion
Who attends Contract Managers, Project Managers and others
Fee from USD 2,200 KSh 190,000 for Kenyan organisations
Where 52 cities + online See dates by city
Next start 16 Nov 2026 Course code SD-CM-138

Before you join: Participants should have practical exposure to projects, procurement, supplier management or operational contracts.

Dates & prices

Two start dates a month in every city, and live online on weekdays or weekends. Fees are per participant; classroom fees include tuition, materials, lunch and refreshments, and the certificate.

Suggest a date or city

Showing the next six months. Later dates, other cities and private deliveries for your team are available on request.

Course overview

Contracts fail most often at the points where commercial intent meets delivery reality: scope is incomplete, risk is allocated without evidence, notices are missed, changes proceed without authority, or claims are assembled after records have disappeared. These failures can lead to disputed invoices, delayed projects, unrecovered costs, damaged supplier relationships and avoidable litigation. Contract managers need a disciplined approach that connects planning, procurement strategy, contract administration and claims preparation from the earliest project decisions.

This course develops the practical methods used to plan and manage contracts through their full lifecycle. Participants assess contract requirements, select delivery and pricing strategies, develop risk allocation positions, prepare negotiation plans and establish administration controls. They work with scope definition, tender evaluation, payment mechanisms, change control, notices, contemporaneous records, delay analysis and claim substantiation. The course also examines common contract forms, including FIDIC and NEC4 principles, and the appropriate use of negotiation, dispute boards, mediation, adjudication and arbitration.

Teaching combines focused briefings with contract clauses, project cases, commercial scenarios, group analysis and structured simulations. Participants apply each method to a continuing case involving a major capital or operational contract, progressively building planning and claims documents. They leave with a reusable contract management pack containing a contract strategy, risk register, administration plan, change-control workflow, notice checklist and claim preparation structure.

The course is suited to professionals managing construction, infrastructure, technology, facilities, procurement, outsourcing, manufacturing and public-sector contracts. It is particularly relevant where contract value, delivery risk, regulatory obligations or supplier dependence require stronger commercial control.

What you will be able to do

  • Develop a contract strategy aligned with project objectives, market conditions and risk appetite
  • Draft a contract management plan with governance, roles, controls and reporting requirements
  • Evaluate risk allocation using risk registers, probability-impact scoring and treatment actions
  • Apply scope definition, pricing and payment mechanisms to reduce contractual ambiguity
  • Administer notices, instructions, variations and records using controlled contract procedures
  • Prepare substantiated claims using entitlement analysis, causation evidence and quantum calculations
  • Select negotiation and dispute-resolution methods for contested contractual issues
  • Present an integrated contract strategy and claims management pack for a live-style case

Benefits of attending

For you

  • Produce contract strategies that connect scope, risk, pricing and governance decisions
  • Recognise notice, record and approval failures before they weaken contractual entitlement
  • Handle variations with clearer authority, valuation and audit trails
  • Build evidence-based claims instead of relying on retrospective assertions
  • Contribute more confidently to negotiations, dispute meetings and senior commercial reviews

For your organisation

  • Fewer uncontrolled scope changes and unauthorised commercial commitments
  • Earlier identification of contractual risks, notice deadlines and recovery opportunities
  • More consistent contract files, correspondence and decision records
  • Better substantiated claims and stronger responses to supplier claims
  • Improved alignment between project delivery, procurement, finance and legal teams

Course modules

20 modules over 10 days

Participants can map contract lifecycle decisions and establish governance for accountable commercial control.

  • Contract lifecycle stages from business case through close-out and lessons learned
  • Commercial governance model defining decision rights, authorities and escalation routes
  • Three-lines model roles for delivery, oversight and independent assurance
  • RACI matrix built for contract approvals, instructions and payment certification
  • Delegated authority limits linked to commitments, variations and claim settlements
  • Contract file structure supporting auditability, retrieval and controlled correspondence

Participants can define contractual requirements that are measurable, complete and commercially usable.

  • Requirements hierarchy linking business needs, specifications, drawings and deliverables
  • Work breakdown structure used to test scope completeness and interfaces
  • Acceptance criteria expressed through measurable performance, quality and handover conditions
  • Assumptions register separating confirmed facts, dependencies and unresolved decisions
  • Interface matrix assigning responsibilities between client, contractor and third parties
  • Scope exclusions written to prevent implied obligations and duplicated responsibilities

Participants can select a delivery and contracting strategy suited to project conditions.

  • Make-buy analysis comparing internal capability, market capacity and strategic control
  • Delivery models including design-bid-build, design-build and EPC arrangements
  • Packaging strategy balancing interface risk, supplier competition and management capacity
  • Single-source justification supported by market evidence and approval criteria
  • Contract duration matched to asset lifecycle, demand certainty and supplier investment
  • Strategic objectives translated into contract performance and commercial requirements

Participants can assess supplier markets and prepare informed sourcing positions.

  • Porter's Five Forces applied to supplier power and market entry barriers
  • Kraljic matrix classifying spend by profit impact and supply risk
  • Should-cost analysis separating labour, materials, overheads, profit and contingency
  • Supplier financial due diligence using liquidity, gearing and cash-flow indicators
  • Market sounding questions testing capacity, innovation and procurement feasibility
  • Competitive tension strategy addressing bidder numbers, lotting and negotiation alternatives

Participants can allocate contractual risks to the party best able to manage them.

  • ISO 31000 risk process applied to contractual threats and opportunities
  • Risk breakdown structure covering technical, commercial, legal and external risks
  • Probability-impact scoring calibrated with defined scales and decision thresholds
  • Risk allocation matrix matching control, insurability and pricing to each party
  • Risk treatment actions covering avoidance, reduction, transfer and acceptance
  • Contingency ownership distinguished from contractor allowances and client reserves

Participants can match pricing and payment mechanisms to scope certainty and risk allocation.

  • Lump-sum pricing assessed against design maturity and change exposure
  • Reimbursable contracts controlled through allowable cost definitions and audit rights
  • Target-cost mechanisms using pain-gain share and agreed cost baselines
  • Unit-rate schedules linked to measurement rules and quantity verification
  • Milestone payments tied to objective acceptance evidence and invoice requirements
  • Price adjustment formulas addressing inflation indices, currencies and exceptional volatility

Participants can plan defensible tender processes and evaluate bids against stated criteria.

  • Procurement plan sequencing approvals, market engagement, tender and award activities
  • Tender timetable allowing bidder questions, clarifications and controlled addenda
  • Evaluation criteria weighted for technical quality, price, risk and delivery
  • Compliance matrix recording mandatory submissions, deviations and qualification responses
  • Whole-life cost evaluation including operations, maintenance, disposal and energy use
  • Evaluation moderation process documenting consensus decisions and conflict declarations

Participants can interpret core contract clauses and identify their operational consequences.

  • FIDIC clause structure covering obligations, payment, variations and claims
  • NEC4 early warning process and compensation event principles
  • Order-of-precedence clauses resolving conflicts between specifications and commercial documents
  • Limitation-of-liability provisions tested against foreseeable loss and insurance coverage
  • Indemnities distinguished from warranties, guarantees and statutory liabilities
  • Force majeure clauses defining events, notice requirements and relief

Participants can prepare structured negotiation plans for contractual and commercial issues.

  • BATNA analysis identifying alternatives when agreement cannot be reached
  • Interest-based negotiation separating underlying needs from stated bargaining positions
  • Negotiation mandate defining objectives, concessions, limits and approval authorities
  • Issue-trade matrix linking concession values to reciprocal commercial returns
  • Anchoring strategy tested against market data and cost evidence
  • Meeting agenda assigning roles, decision points and documented actions

Participants can create a contract management plan that governs post-award delivery.

  • Contract management plan covering governance, controls, reporting and key dates
  • Obligations register capturing deliverables, owners, due dates and evidence
  • Key performance indicators linked to service levels and contract objectives
  • Contract calendar tracking notices, renewals, certifications and review meetings
  • Document control protocol defining versioning, transmittals and authorised repositories
  • Management information dashboard reporting performance, risk, changes and disputes

Participants can control mobilisation and manage contractor performance against agreed obligations.

  • Mobilisation checklist covering securities, insurances, programmes and key personnel
  • Kick-off agenda confirming interfaces, reporting, communications and escalation arrangements
  • Service-level measurement using baselines, targets, tolerances and remedy triggers
  • Performance review meetings structured around evidence, actions and accountabilities
  • Corrective action plans addressing root causes, owners and completion dates
  • Supplier relationship segmentation distinguishing transactional, managed and strategic arrangements

Participants can issue timely contractual notices and maintain records that protect entitlement.

  • Notice register tracking contractual deadlines, recipients, delivery methods and responses
  • Notice drafting states event, clause, impact, reservation and required action
  • Without-prejudice correspondence distinguished from open contractual communications
  • Contemporaneous records include diaries, photographs, minutes and progress reports
  • Meeting minutes record decisions, dissent, actions and contractual reservations
  • Evidence retention schedule aligned with limitation periods and audit requirements

Participants can administer changes through authorised instruction, valuation and record procedures.

  • Change-control workflow from request identification through approval and implementation
  • Variation instruction requirements covering authority, scope, timing and valuation basis
  • Change register tracks status, cost forecast, schedule effect and decisions
  • Valuation methods compare agreed rates, fair valuation and quotation analysis
  • Unauthorised work response preserves rights while maintaining operational continuity
  • Configuration management controls revised drawings, specifications and approved baselines

Participants can manage payment certification, cost evidence and contractual financial recovery.

  • Payment application review checks progress evidence, rates, deductions and tax
  • Certification workflow defines reviewer roles, approval thresholds and payment dates
  • Cash-flow forecast compares planned, earned, invoiced and paid values
  • Retention provisions managed through release conditions, defects and final account
  • Set-off rights assessed against notice requirements and undisputed payment obligations
  • Open-book audit tests invoices, timesheets, purchase records and cost allocation

Participants can assess time-related events and identify evidence for delay and disruption claims.

  • Critical path method identifies activities governing contractual completion dates
  • Baseline programme review tests logic, durations, calendars and resource assumptions
  • Time impact analysis models prospective effects of discrete delay events
  • Windows analysis compares planned and actual critical paths across periods
  • Concurrent delay assessment identifies overlapping causes and contractual treatment
  • Disruption evidence links productivity loss to records, outputs and causation

Participants can prepare claims that connect contractual entitlement, facts, causation and quantum.

  • Claim structure presents entitlement, facts, causation, quantum and requested relief
  • Clause analysis identifies conditions precedent, notice periods and remedy provisions
  • Chronology prepared from correspondence, records, instructions and programme updates
  • Causation analysis separates triggering events from downstream cost consequences
  • Quantum calculations substantiate prolongation, disruption, acceleration and financing costs
  • Claim narrative cross-references evidence using indexed document and exhibit schedules

Participants can evaluate incoming claims and prepare evidence-based contractual responses.

  • Claim triage assesses value, urgency, entitlement strength and settlement options
  • Response matrix tests each allegation against clauses, facts and records
  • Reservation-of-rights letters preserve contractual positions without premature admissions
  • Counterclaim identification addresses defects, delay damages and overpayment recovery
  • Expert evidence scope defines questions, data sources and independence requirements
  • Settlement authority matrix controls offers, concessions and documented approvals

Participants can select proportionate dispute-resolution routes and prepare for formal proceedings.

  • Dispute escalation ladder sets negotiation, mediation and adjudication decision points
  • Dispute boards provide contemporaneous recommendations or binding determinations
  • Mediation preparation identifies interests, settlement ranges and decision authority
  • Adjudication timetable requires focused evidence, submissions and rapid response coordination
  • Arbitration clause specifies seat, rules, tribunal and language requirements
  • Settlement agreement terms address releases, confidentiality, payment and enforcement

Participants can close contracts systematically while preserving final rights and organisational learning.

  • Close-out plan confirms deliverables, certificates, records and final payment milestones
  • Final account reconciliation resolves quantities, variations, claims and outstanding deductions
  • Defects liability tracking records notifications, remedies and release conditions
  • Asset handover verifies manuals, training, warranties and operating documentation
  • Post-contract review captures commercial outcomes, root causes and corrective actions
  • Lessons-learned register assigns owners, actions and future procurement application

Participants can build, review and present a complete contract strategy and claims management pack for a contested project scenario.

  • Contract strategy integrates scope, market analysis, delivery model and pricing
  • Risk allocation matrix assigns ownership, treatment actions and contractual mechanisms
  • Administration plan establishes governance, notices, records and change controls
  • Claim dossier assembles entitlement analysis, chronology, evidence and quantum
  • Negotiation position sets objectives, trade-offs, settlement boundaries and approvals
  • Peer review tests consistency, evidence gaps, contractual exposure and presentation

Exercises and examples are adapted to each cohort's sectors and roles.

What you take back to work

  1. Contract strategy template
  2. Contract risk allocation matrix
  3. Contract management plan template
  4. Notice and correspondence checklist
  5. Variation control workflow
  6. Claims preparation dossier structure

Who should attend

  • Contract Managers — responsible for commercial control from award through close-out
  • Project Managers — need to protect delivery decisions through disciplined contract administration
  • Procurement Managers — shape sourcing, tender and award strategies before contractual commitments
  • Commercial Managers — manage risk, payment, variations and disputed cost recovery
  • Engineers and Technical Leads — issue instructions and manage scope changes with contractual authority
  • Legal and Compliance Professionals — support contractual risk, notices and dispute preparation

Skills and tools covered

Contract strategy developmentRisk allocation analysisContract administrationChange controlClaims preparationDispute resolution

Tools and standards

FIDIC Conditions of Contract, NEC4 Engineering and Construction Contract, ISO 31000, Kraljic Matrix

How the course runs

Training methodology

Instructor-led sessions combine short technical briefings with clause review, worked commercial cases, facilitated group analysis and negotiation simulations. Participants analyse a continuing contract scenario, applying planning and administration methods as new events arise. Discussions compare alternative contract positions, evidence requirements and response options. Trainers provide structured feedback on draft strategies, risk allocations, notices and claim narratives. Individual application planning helps participants adapt the methods, templates and controls to their own contract portfolio after the course.

Requirements and prerequisites

Participants should have practical exposure to projects, procurement, supplier management or operational contracts. They should be comfortable reading contract clauses, purchase orders, scopes of work and basic commercial correspondence. Experience with contract administration, tendering or project controls is useful but not essential. The course assumes no legal qualification and does not require prior use of FIDIC, NEC4, formal claims analysis software or scheduling software. It is designed for professionals who need to make or support informed commercial decisions rather than provide legal advice.

A typical training day

08:30 – 10:30First session
10:30 – 10:45Refreshment break
10:45 – 12:30Second session
12:30 – 13:30Lunch and networking
13:30 – 15:00Third session
15:00 – 15:15Refreshment break
15:15 – 16:30Workshop and daily review

Live online deliveries follow the same structure in East Africa Time, with shorter screen blocks and longer breaks.

What the fee includes

  • Instruction by a practitioner facilitator
  • Full course workbook and materials
  • Exercise files, templates and case studies
  • Refreshments and lunch on classroom deliveries
  • Certificate of completion
  • Post-course application plan

Frequently asked questions

Participants should have worked with projects, procurement, suppliers or operational contracts and be able to read basic contract documents. A legal qualification is not required, and the course does not assume prior FIDIC, NEC4 or claims software experience.

Bring a non-confidential contract, scope of work, change issue or claims challenge from your workplace if possible. These materials can be used during application planning, provided no restricted information is shared.

It is designed for contract, commercial, project, procurement, engineering and legal professionals who manage supplier or client obligations. It suits professionals with some exposure to contracts who need more systematic planning, administration and claims skills.

The course focuses on the operational and commercial work of managing contracts after and before award: strategy, risk, records, changes, payments and claims. It explains clause consequences but does not train participants to give legal advice or replace specialist counsel.

Participants leave with reusable templates for strategy, risk allocation, administration, notices, variations and claims. They can use these tools to improve a current contract file, project review process or supplier governance meeting.

Training runs from 08:30 to 16:30 each day, with about 6.5 contact hours. The first part establishes contract planning and administration controls; the later sessions address claims, disputes, close-out and a final integrated case presentation.